Bi-Weekly Construction Update - February 6th, 2026
Two-Week Look Ahead
Crews will be completing site preparation work, including:
Backfilling for leveling and stabilizing of the site will be completed
Demolition equipment will be demobilizing from site
Will mobilize drilling equipment for soil testing drilling
Temporary Impacts to Be Aware Of
During this time, neighbours may notice:
Dump trucks delivering clean fill and gravel
Existing equipment being removed from site and new Equipment being delivered to site
Flag personnel will be on site to help manage traffic and support safe movement for drivers, cyclists, and pedestrians. We will continue to take steps to minimize disruption and appreciate the community’s understanding as this work progresses.
Working Hours
Construction activities will be carried out in accordance with the City of Toronto Noise By-law. Work is permitted Monday to Friday between 7:00 a.m. and 7:00 p.m., and Saturdays between 9:00 a.m. and 7:00 p.m. No construction activity is permitted on Sundays or statutory holidays.